Importing tasks and due dates into SPM from MS Project

$
0
0

Has anyone successfully managed to import tasks into SPM projects?  Specifically, I am trying to set due dates at a project level by exporting my tasks, updating the due dates in MS Project and importing back into the project.  The import action just replicates the same task underneath my existing tasks even if I instruct it to overwrite matching tasks.

 

Would welcome input from anyone who has any tips on how to get this working properly......thanks Neil